Please solve each subpart. 10. A process is made up of six activities with the following…

Please solve each subpart.
10. A process is made up of six activities with the following task times: Activity A 4 minutes 6 minutes 16 minutes 5 minutes | 7 minutes 2 minutes Daily available production time is 480 minutes with a daily demand of 60 units. a. Calculate the takt time for this process. Interpret. b. Based on this take time and the activity times provided, what is the minimum number of stations needed for this process? c. Create a load chart or a visual allocation of the six activities to these stations such that no stations’ total time is greater than takt time. What is the resulting buffer (based on takt time) at each station?